Curved conveyor route inside Symbion’s pharmaceutical distribution facility
← Projects & Proven Results
Symbion · Pharmaceutical Distribution

Four Kilometres.
One Connected
Conveyor Network.

Conveyor assembly, installation and testing for Symbion’s pharmaceutical wholesale distribution facility, delivered by ACS for SSI SCHAEFER.

ACS’s Client SSI SCHAEFEREnd Client Symbion
Explore The Installation
4 kmConveyors Installed & Tested
5 MonthsProject Delivery
28 PeopleProject Team Members
The Project

Conveyor Installation
For Pharmaceutical Distribution.

A five-month installation programme. Four kilometres of conveyor. A coordinated team of 28 people.

ACS worked for SSI SCHAEFER on a conveyor installation for Symbion, a pharmaceutical wholesaler. The project supported a distribution facility with medicine storage capabilities, including cold storage, within an automated logistics environment.

Our role centred on the mechanical assembly and installation of conveyor lines, followed by testing. By bringing the conveyor sections together across the facility, the ACS team helped turn the material-handling layout into a connected conveyor network.

Connecting The Conveyor Routes
The Team Behind The Project

Planning The Day.
Delivering Together.

An early meeting brings the ACS team together to plan the day’s work. A closer look at the people and coordination behind the Symbion conveyor installation.

Early-Morning Planning With The ACS Project Team
Installation Work On The Conveyor Network
Assembly & Installation

The Work Behind
Every Conveyor Section.

Hands-on mechanical assembly across a four-kilometre conveyor installation.

The work involved assembling the conveyor sections and installing them as part of the wider distribution network. ACS’s mechanical team worked through the conveyor lines, bringing the individual sections together across the site.

With 28 team members on the project, coordination connected day-to-day assembly work with the overall five-month programme. This was a substantial installation built through the practical work of the people on site.

Testing & Delivery

Installed.
Connected. Tested.

The project scope carried through from conveyor assembly to testing the installed lines.

Four Kilometres Of Conveyor

ACS assembled and installed conveyor lines across Symbion’s pharmaceutical distribution facility, bringing together the sections that formed the conveyor network.

Testing The Installation

Testing formed part of ACS’s work on the installed conveyors, following the mechanical assembly and installation activities.

A Five-Month Programme

The project was completed over five months, with an ACS team of 28 people working for SSI SCHAEFER.

Belt Conveyor Routes Across The Site
Inside The Project

A Closer Look At The Site.

Site photography from the Symbion project. Select a photograph to view the full image and explore the facility around the conveyor installation.

Plan Your Next Installation

Conveyor Expertise
For Your Next Facility.

Talk to ACS about mechanical assembly, conveyor installation and project support.

Discuss Your Project