Install Site Electrical Infrastructure
Establish the electrical infrastructure needed to connect the processing equipment and container systems at the new facility.
A complete electrical installation for GoTerra’s new Wetherill Park processing facility, delivered in one month by a ten-person ACS team.
Explore The ProjectGoTerra needed the electrical infrastructure and equipment connections to establish its new processing facility in Wetherill Park.
ACS delivered the core electrical build: a new mains supply and distribution board, machine power connections and container electrical fit-outs. The work supported the factory process from food waste crushing through to transfer and container-based handling.
The installation was delivered in one month by a team of ten people. The electrical systems were tested and verified as required, leaving the facility ready for commissioning.
Ten ACS team members delivered the new electrical installation over one month, bringing practical site work and coordination together across the build.
Establish the electrical infrastructure needed to connect the processing equipment and container systems at the new facility.
Supply and install the distribution board and related electrical infrastructure, including mains and machine supply connections.
Provide power installation and connections for food crushers and transfer systems feeding into the processing containers.
Modify and fit out container electrical systems to suit crate handling, equipment interfaces and space requirements, then test and verify the installations for commissioning.
Site power, processing equipment and container systems connected through one coordinated electrical installation.
Equipment, containers and electrical work needed to come together as the site’s process details developed.
Process requirements and container layouts continued to develop, requiring the electrical work to be coordinated with the latest site needs.
Equipment connections and container interfaces required careful sequencing so installation activities supported the wider process flow.
Tight spaces inside the containers required careful access planning and installation work, with safety and compliance kept central to delivery.
ACS handed over the electrical installation ready to support commissioning and production start-up.
The new facility was equipped with a functional distribution and machine supply setup.
Electrical connections supported the process from the food crusher through to transfer and container handling.
Required installation testing and verification prepared the systems for the next stage of site commissioning.