Plan & Coordinate
Work with Pact’s reliability team on permits, SWMS, contractor meetings and shutdown sequencing.
Electrical disconnection and reinstatement for Pact’s production line relocation from Ash Road to Pascoe’s, coordinated around tight operational windows.
Explore The Case StudyPact Group needed production lines disconnected, relocated by third-party movers and electrically reinstated within demanding operational windows.
ACS planned the electrical works with Pact’s reliability team, coordinating shutdown sequencing, contractor meetings, permits and safe work method statements (SWMS). The scope connected disconnection at Ash Road with staged electrical tasks at Pascoe’s and support for recommissioning.
Production priorities and mechanical readiness changed the programme along the way. ACS coordinated materials, site interfaces and the order of work so rough-in cabling and final supply-end terminations aligned with access and the distribution board changeover.
Work with Pact’s reliability team on permits, SWMS, contractor meetings and shutdown sequencing.
Disconnect production lines, including Industrial line works, and coordinate the interface with third-party relocation contractors.
Complete rough-in cabling, general-purpose power outlets (GPOs), terminations and board/distribution board changeover support.
Supply and manage materials, complete minor fabrication such as a control panel frame, and support recommissioning to restore production readiness.
The supplied photographs show production equipment and facility environments associated with the case study. The electrical scope focused on disconnection, staged reinstatement and the interfaces needed for return to service.
Line reinstatement required electrical tasks to be sequenced with mechanical readiness and the movers’ programme.
Materials, access and staged electrical work were managed around changing dates and the distribution board interface.
Production priorities and mechanical readiness led to date changes and stand-down days, requiring ongoing coordination.
Tight remove, relocate and reinstate windows needed to align with Pact’s required operational targets.
Multiple sites and contractors had to coordinate rough-in works, supply-end terminations and the distribution board swap.
The relocation was delivered through clear staging and coordination, with electrical works aligned to Pact’s production constraints.
Cabling, GPOs, terminations and the board/distribution board interface supported the lines’ return to operational status.
Shutdown tasks were planned with the reliability team and coordinated with the relocation and mechanical works.
Materials, permits, SWMS and site interfaces were managed to reduce downtime risk and maintain progress despite schedule changes.