Verify & Disconnect
Check the machine running before work, disconnect cabling and hydraulics, and dismantle guarding and fencing for transport.
Electrical and mechanical relocation of industrial MEP machines from Wetherill Park to St Marys, with each machine disconnected, moved, reassembled and tested in sequence.
Explore The Case StudyOriem needed industrial MEP machines moved from Wetherill Park and reinstalled at St Marys to suit the new floor layout.
ACS coordinated electrical and mechanical disconnection, the transport interface, reassembly, reconnection and operational testing. Guarding and fencing formed part of the move, alongside the machinery and its services.
The work progressed one machine at a time. Each machine’s operating condition was checked before disconnection, then it was relocated, reconnected and function-tested with a trained MEP operator before return to service.
Two timelapse views from the Oriem relocation, showing the site team preparing and handling machinery during the disconnection stage.
Both timelapses play automatically, muted, when this section comes into view. Use the controls to pause or watch in full screen.
A closer view of the site team and machinery handling.
A wider view of the preparation and handling sequence.
A staged approach kept disconnection, movement and return-to-service checks focused on one machine at a time.
Check the machine running before work, disconnect cabling and hydraulics, and dismantle guarding and fencing for transport.
Coordinate with the transport and crane provider, unload at St Marys, and reassemble the machine and guarding to Oriem’s layout.
Reconnect electrical and mechanical services and fix the machinery and fencing in place.
Energise and function-test with a trained MEP operator, then complete sign-off and documented close-out.
The transport and crane interface needed to align with disconnection, access and the receiving site’s readiness. These photographs show the handling of machinery and associated assemblies.
A multi-machine move required coordination between site readiness, access, trades and transport.
Each relocation followed its own disconnect-to-test sequence, helping manage restart risk and maintain control of commissioning.
Access delays and changes to move-in timing required schedule management around the receiving site.
Electrical and mechanical crews coordinated with the transport provider to keep disconnection, movement and reconnection aligned.
At St Marys, ACS reassembled the machines and guarding to the agreed layout, reconnected the services and secured the equipment for operational testing.
The industrial machines were relocated, reinstalled and returned to operational condition at St Marys, with sign-off.
Electrical and mechanical reconnection was followed by function-testing with a trained MEP operator.
The one-machine-at-a-time approach reduced restart risk by keeping each disconnection, move, reconnection and test sequence together.
The relocation was delivered within the standard working-hours plan, with coordinated crews and documented close-out.
Further views of the site team preparing machine assemblies, coordinating transport and positioning equipment during the relocation.
Talk to ACS about coordinated electrical and mechanical support for machinery disconnection, relocation, reinstallation and testing.