Assess The Areas
Review the crane route, the three main operating areas and the points where people needed access.
A major upgrade to gated access and safety controls across three crane operating areas, delivered during CSR Hebel’s four-week Christmas shutdown.
Explore The Case StudyCSR Hebel’s crane transferred parts between three large operating areas, creating an interface between overhead material movement and people accessing the plant.
ACS began by assessing the work areas and access routes. The upgrade brought together mechanical access measures and electrical safety controls: gated pathways, safety sensors and a safety PLC to coordinate the response to access or detection events.
A 27-person team worked 12-hour days within the four-week Christmas shutdown window. The focus was to better control access and bring the relevant equipment to a safe stop when a safety input was triggered.
Views across the plant show the scale of the operating areas and the relationship between crane movement, equipment and access routes.
Review the crane route, the three main operating areas and the points where people needed access.
Provide gates at pathway access points as part of the mechanical measures around the operating areas.
Use a safety PLC with gate and sensor inputs to coordinate the electrical safety response.
Configure the safety response so an access or sensor trigger brings the relevant crane and plant movement to a safe stop.
Project overview of the safety approach.
The pathway gates formed the physical access measures around the crane areas. Local controls and indicators provided a visible interface at the access points.
The safety PLC and connected inputs brought the access measures into the electrical control system. A triggered safety input initiated the response needed to stop the relevant movement, helping reduce exposure to the crane’s operating area.
The Christmas shutdown provided four weeks to carry out a major upgrade across large, interconnected operating areas.
A substantial site team supported the mechanical access work and electrical safety installation within the shutdown programme.
The team worked extended days to progress the upgrade during the available shutdown period.
Coordination had to consider the crane’s travel across all three areas alongside the people, pathways and access points below.
ACS delivered a major safety upgrade combining gated pathways with safety PLC control across the crane operating areas.
Gates provided defined access points around the crane and connected work areas.
Safety input triggers were linked to stopping the relevant equipment movement, supporting risk reduction where people and machinery interact.
The mechanical and electrical work was coordinated within the four-week Christmas shutdown programme.